Environmental Management Citeureup Factory
Download the complete Document in PDF format (477 KB)
Executive Summary:
The Citeureup Cement Factory maintains an accredited ISO 14000:1996 Environmental Management System to take precaution against and to manage adverse negative environmental and social impacts caused by its cement production. The company voluntarily participates in the Blue Sky Program and the Proper Program, both initiated by the Government of Indonesia to improve environmental conditions in Indonesia. The Citeureup Cement Factory is in compliance with the environmental management and monitoring commitments developed in the Environmental Impact Assessment study and stated in the Environmental Management Plan (RKL) and Environmental Monitoring Plan (RPL) documents.
The Environmental Management Plan combines the various individual environmental and social management programs that are in place at the Citeureup Cement Factory. It also includes the management response to process changes related to the Clean Development Mechanism project.
The Citeureup Cement Factory is operated by PT. Indocement Tunggal Prakarsa Tbk. (Indocement), consisting of 9 kilns and occupying in total about 2,700 ha land including raw material mining. The factory is strategically located about 45km south of Jakarta to supply cement to Metropolitan Jakarta and West Java. The cement production process consists essentially of raw materials mining, crushing, drying, grinding, kiln burning, cooling, finish grinding, packing and shipping. The raw materials used are limestone, sandy clay, silica, and iron sand.
The Clean Development Mechanism (CDM) project includes the introduction of additive materials into finish grinding, and the use of alternative fuels. Various alternative fuels will be envisaged such as Biomass, waste tyres, waste oils, plastics, papers, textiles, etc. Use of different types of alternative fuels is subject to further studies and relevant Government permits.
Dust and gaseous emission are recognized as the prime adverse environmental impact in the cement industry. Social challenges arise from the need of a high number of employees and the need for mining areas. Material handling imposes significant stress on the local transportation infrastructure. Process changes due to the CDM project may be perceived as negative and detrimental to the environment.
This Environmental Management Plan outlines a series of Impact Mitigation and Monitoring Plans to address these environmental and social challenges. Individual plans exist for:
- Air, Noise, and Vibration
- Surface and Groundwater
- Land and Topography
- Flora and Fauna
- Hazardous Materials/Waste
- Worker Health & Safety
- Public Consultation and Participation
- Community Development Program:
- Education
- Social culture
- Infrastructure
- Economic
- Public Health
The implementation of the Environmental Management Plan is embedded in an ISO 14000 accredited Environmental Management System. The Environmental Management System outlines environmental objectives and targets, institutional requirements, responsibilities and authority, as well as requirement for financial and human resources.
Download the complete Document in PDF format (477 KB)
|